2009-08-19 Today, even though it\'s raining we are installing the windows. It\'s...
2009-08-15 Now we are installing the toilet, showers, water system... yet another...
2009-08-10 floors are finished but not varnished yet... we started electrical wiring....
2009-08-01 We started to lay down the floor of the bungalows... some small trouble...
2009-07-14 11 bungalows getting ready, roofs in place... it will take more time...
2009-07-01 here we are, the bungalows are being built, the website is now up and...
2009-09-03TEST2009-08-19Today, even though it\'s raining we are installing the windows. It\'s funny since they came without the glasses for which we will have to wait for another week (or may be more). no more riding now, the wind seems to be dead until the next season...2009-08-15Now we are installing the toilet, showers, water system... yet another strange experience. Add to this that wind has been blowing continously for a month, that the tentation to ride instead of working was so big that we could not resist and you will understand how hard it is. Anyway, we are still on track and within the schedule2009-08-10floors are finished but not varnished yet... we started electrical wiring. Another tremendous task as the local standard are far away from what we are used to... Anyway with a bit of talking we could get them to do it properly2009-08-01We started to lay down the floor of the bungalows... some small trouble as can be expected, but it looks good. we will have a lot of work to make the floor flat, since the workers are a bit careless2009-07-1411 bungalows getting ready, roofs in place... it will take more time to complete everything but we are on schedule 12>>
Activities
Accomodation
Booking
Contact us
Find us
Price list